Question 25
Which of the following is NOT an objective of service transition?
A. To ensure that a service can be operated, managed and supported
B. To provide training and certification in project management
C. To provide quality knowledge and information about services and service assets
D. To plan and manage the capacity and resource requirements to manage a release
Answer: B
Wednesday, 14 December 2016
Monday, 28 November 2016
New & Updated ITILFND Exam Questions
Question 24
What is the name of the group that should review changes that must be implemented faster than the normal change process?
A. Technical management
B. Emergency change advisory board
C. Urgent change board
D. Urgent change authority
Answer: B
What is the name of the group that should review changes that must be implemented faster than the normal change process?
A. Technical management
B. Emergency change advisory board
C. Urgent change board
D. Urgent change authority
Answer: B
Monday, 21 November 2016
Latest & Updated ITILFND Exam Question Answers
Questions 23
What would you call the groups of people who have an interest in the activities, targets, resources and deliverables from service management?
A. Employers
B. Stakeholders
C. Regulators
D. Accreditors
Answer: B
What would you call the groups of people who have an interest in the activities, targets, resources and deliverables from service management?
A. Employers
B. Stakeholders
C. Regulators
D. Accreditors
Answer: B
Friday, 18 November 2016
ITIL ITILFND Exam Questions
Question 22
What are the categories of event described in the UIL service operation book?
A. Informational, scheduled, normal
B. Scheduled, unscheduled, emergency
C. Informational, warning, exception
D. Warning, reactive, proactive
Answer: C
What are the categories of event described in the UIL service operation book?
A. Informational, scheduled, normal
B. Scheduled, unscheduled, emergency
C. Informational, warning, exception
D. Warning, reactive, proactive
Answer: C
Saturday, 23 July 2016
ITIL ITILFND Exam Study Material
Question 21
Which process is responsible for managing relationships with vendors?
A. Change management
B. Service portfolio management
C. Supplier management
D. Continual service improvement
Answer: C
Which process is responsible for managing relationships with vendors?
A. Change management
B. Service portfolio management
C. Supplier management
D. Continual service improvement
Answer: C
Saturday, 25 June 2016
Get Actual ITILFND Exam Question Answer
ITILFND Question 20
What is the result of carrying out an activity, following a process or delivering an IT service known as?
A. Outcome
B. Incident
C. Change
D. Problem
Answer: A
What is the result of carrying out an activity, following a process or delivering an IT service known as?
A. Outcome
B. Incident
C. Change
D. Problem
Answer: A
Saturday, 14 May 2016
Latest & Updated ITILFND Exam Questions
ITILFND Question 19
Which one of the following is NOT part of the service design stage of the service life cycle?
A. Designing and maintaining all necessary service transition packages
B. Producing quality, secure and resilient designs for new or improved services
C. Taking service strategies and ensuring they are reflected in the service design processes and the service designs that are produced
D. Measuring the effectiveness and efficiency of service design and the supporting processes
Correct Answer: A
Which one of the following is NOT part of the service design stage of the service life cycle?
A. Designing and maintaining all necessary service transition packages
B. Producing quality, secure and resilient designs for new or improved services
C. Taking service strategies and ensuring they are reflected in the service design processes and the service designs that are produced
D. Measuring the effectiveness and efficiency of service design and the supporting processes
Correct Answer: A